TOKUA AIRPORT UNDER MAINTENANCE

THE long-awaited repair work on the Tokua Airport runway in Kokopo District, East New
Britain province, commenced last Tuesday.

The project, funded by the National Airports Corporations (NAC) at a cost of K12 million, will take four months to be completed by contractor Hebou Constructions Limited.

The airport is currently undergoing pavement repairs and overlaying of asphalt on the
300 meters by 12 meter damaged part (pothole) of the 1, 720-meter runway, that was
believed to have been caused around the early 2000s as heavier aircraft were
introduced to the airport.

The damaged part of the runway has reduced its length since; thus, airliners
downgraded their services to smaller planes like Dash 8 and Q400.

The maintenance work is carried out on the central part of the runway by the contractor.

ENB Governor, Michael Marum and Gazelle MP Jelta Wong visited the work site a day after the commencement.

The reconstruction work covers excavation of pavement, construction of cement treated
basecourse pavement, asphalt overlay and grooving, runway line markings and
drainage improvement.

Mr Russel Paliai said: ” that the runway repair is on stage one which will cover a length of 850 meters by 12 meters width and will take a duration of 6 weeks.”

Paliai is the Tokua Operations Manager for National Airports Corporation (NAC).

“The runway is reduced by 850 meters and we are only expecting Dash 8 to land. The
first stage involves the removal of the old asphalt, then the laying of cement, followed by
placing of newer asphalt,” he said.

Hebou Construction Ltd shipped the asphalt materials from Port Moresby and the
asphalt plant and pugmill from Lae for the maintenance work on the runway.

The repair work is aimed at fixing the damages on the 1,720-meter runway, and to build
a stronger pavement that is durable and can withstand the weight of bigger planes.

━ Related News

ITI hosts AI Summit 2026 to raise awareness and explore practical applications

The second AI Summit, which will start this Friday at the Stanley Hotel in Port Moresby, has attracted 400 attendees and 19 local and...

PM Marape, World Bank hold talks on PNG’s shift from extractive industry to inclusive agriculture growth

Prime Minister, James Marape this week held high-level bilateral discussions with senior World Bank Group executives at Melanesian Haus in Port Moresby, focusing on...

K1.97 billion worth contract signed for Pom-Central-Milne Bay, Sepik Coastal Highway

K1.97 billion worth contracts for Sepik Coastal Highway and new trans-National Highway to Milne Bay from Port Moresby via Central province were signed today...

Sir John to launch National Firearms Amnesty and guns buy-back policy in Wabag

Police Minister Sir John Pundari says the official launch of the National Firearms Amnesty and Buy-Back Program is set on Friday, March 6, in...

PM Marape requests foreign consular support for evacuation of PNG citizens from UAE

Prime Minister, James Marape has requested foreign consular assistance to support the possible evacuation of Papua New Guinean citizens currently in the United Arab...